63rd Extension Week 4 Update

63rd Extension Week 4 Update

Hi Everyone- I hope you are having a great start to the week!  Here is the weekly update for the 63rd street project: The past week: This past week, we completed grading activities at the Brady/Schone/Silver properties and continued tree removal, bank and instream...
63rd St Extension Week 3 Update

63rd St Extension Week 3 Update

03/22/2018 Hi Everyone- I hope you are having a great week! Here is the weekly update for the 63rd street project: The past week: This past week, we continued work in our phase I project area, grading the banks and installing instream channel features. We also...
63rd St Extension Week 2 Update

63rd St Extension Week 2 Update

03/14/2018 Hi Everyone- I hope you had a great week. The past week: This past week, we mobilized into the phase I project area, completed all necessary pre-construction activities, began tree removal, and started instream excavation work. A look ahead: • Over the next...
63rd St Extension Week 1 Update

63rd St Extension Week 1 Update

    03/05/2018 Hi Everyone- This is the start of the weekly updates for the 63rd street extension project. Please let me know if anyone should be added or removed from this list. We have posted designs and the draft construction schedule on our website:...